(Summary description)With the continuous development of the market economy, various new technologies have been introduced and developed, and new products have emerged in an endless stream and are widely used in construction projects. Compared with traditional products, they have great advantages in terms of manufacturing process, material properties, product quality or production cost, installation technology and construction methods. One example is the single-core branch cable and the traditional compact busway.

Comparison and analysis of two schemes of branch cable and busway in busway engineering example

(Summary description)With the continuous development of the market economy, various new technologies have been introduced and developed, and new products have emerged in an endless stream and are widely used in construction projects. Compared with traditional products, they have great advantages in terms of manufacturing process, material properties, product quality or production cost, installation technology and construction methods. One example is the single-core branch cable and the traditional compact busway.

  • Categories:Zhongrui News
  • Author:
  • Origin:
  • Time of issue:2019-05-28 13:58
  • Views:
Information
With the continuous development of the market economy, various new technologies have been introduced and developed, and new products have emerged in an endless stream and are widely used in construction projects. Compared with traditional products, they have great advantages in terms of manufacturing process, material properties, product quality or production cost, installation technology and construction methods. One example is the single-core branch cable and the traditional compact busway.
 
Comparison and analysis of two schemes of branch cable and busway in engineering examples
 
The “15~24-story lighting” load of an office building is planned to be trunk-type power distribution. The wiring in the 15~24-layer electrical pipe is laid by single-core branch cable or compact busway.
 
The actual wiring is as follows:
 
(1) Single-core cable is used from the substation low-voltage distribution line to the 14-story electric pipe to make the top branch cable transfer box (or the busway inlet box), and the line length is 80m.
 
(2) The load capacity of each lighting main box (15~24PM) is the same, and the power factor cosψ=0.8 (has passed the capacitance compensation). The mains load requires a factor of K = 0.8.
 
(3) For comparison, it is assumed that the load capacity of each layer is six, 50, 40, 30, 25, 20, and 16 kW, respectively.
 
(4) The cable is made of XLPE insulated vinyl chloride sheathed copper core cable, and the busway is densely insulated.
 
Because of the two schemes, the same single-core cable is used to lay along the bridge from the low-voltage power distribution cabinet to the 14-story electric tube well cable transfer box (or busway cable box), so the comparison of their material prices is only estimated. The vertical pipe can be used to make the material cost of the main line in the well. Table 2 compares the price of the main materials and accessories of the two schemes (the busway adopts 3-phase 4-wire system, and the cable uses 4 single-core branch cables, because the busbar branch line is used in both schemes, one is polyethylene Single-core cable, one is a rubber sheathed flexible cable, the price is not much different, so it is not in the comparison).

Scan the QR code to read on your phone

ABOUT US

 

 

Introduction

 

Business

 

Win-win

 

Advantage

 

Contact us

NEWS

 

 

Zhongrui News

 

Industry

 

FAQ

 

Support

 

CONTACT US

Add:92 Weier Road, Chengbei Park, Jingjiang Economic and Technological Development Zone, Jiangsu Province 

Phone

Mobile version